Sunday's nationwide power outage was caused by an overload in the Kisumu - Muhoroni power line.
According to Energy Cabinet Secretary Davis Chirchir, the Kisumu - Muhoroni line was planned to carry 80MW but was carrying 149MW.
Addressing the press on Monday, December 11, Chichir said that the government will be setting up a new substation and a line of 90km that will relieve the capacity on the Muhoroni - Kisumu line.
"We will build a new 33KV line between Narok and Bomet to prevent constant power outages. We will have reduced overload line to prevent plunging the country into darkness which is not right," he said.
READ MORE
Experts call on farmers to grow drought resilient crops
Regulation of fintech must promote stability and innovation
Ongoing labour unrests are early signs of an economy that's about to collapse
Trailers and weighbridges: The untold story
KTDA moves to restore order in tea bonus declarations
Madagascar tycoon to buy Zuku parent firm Wananchi Group
How container cash deposits are creating a problem for Kenyan traders
Gold rush: How illegal gallbladder trade threatens Lake Victoria fishers
Real estate posts high productivity as challenges hit wholesale, retail sectors
The CS stated that his Ministry has not invested much in the networks and that there are plans to give out a number of networks to be built by private firms. This will ease putting pressure.
"Kenya has not had any major electricity system upgrades for the past 6 years and the new line will take 20 months to complete. It will be funded by the African Development Bank and Japan," the CS added.
Chirchir was among passengers who remained stranded at the Jomo Kenyatta International Airport (JKIA) on Sunday night.
"I was flying in from Dubai, I was at the airport when the electricity went off. I experienced firsthand the anger because as passengers, we could not obtain our bags. The luggage belt was not moving. It is such a shame and we need to address it," he said.
Earlier on Monday, Transport CS Murkomen called on police to investigate possible sabotage after a generator failure at JKIA last night.
- How last minute changes led to Raila's ODM shake-up
- Can KMRC overcome hurdles to spur mortgage uptake?