Lake Turkana wind power flows again after grid line restored

Business
By David Njaaga | Sep 29, 2025

Restored Loiyangalani to Suswa transmission line now carries up to 300MW of wind energy into Kenya’s national grid. [File, Standard]

Households and businesses that have endured repeated blackouts tied to the Loiyangalani to Suswa line will soon get more reliable power after the 400kV link was rebuilt.

The Sh207 million project by the Kenya Electricity Transmission Company (Ketraco) replaced six collapsed towers near Longonot and reconnected two circuits, restoring the line to full operation.

Crews also installed new conductor stringing and Optical Ground Wire (OPGW) to stabilise transmission and improve grid efficiency.

Energy Cabinet Secretary Opiyo Wandayi said the restored capacity will allow the evacuation of up to 300 megawatts (MW) from the Lake Turkana Wind Power (LTWP) project, Africa’s largest wind farm.

 “This improved reliability in power supply will boost investor confidence and assure consumers of consistent access to electricity, which is critical for economic growth,” he said in a statement.

Ketraco Acting Managing Director Kipkemoi Kibias said having both circuits running reinstates N-1 contingency, meaning the grid can withstand faults without major disruptions.

“With both circuits now fully operational, we have restored the grid’s resilience and efficiency,” Wandayi noted, adding, “This reduces outages and cuts costs previously incurred in maintaining temporary bypass infrastructure.”

The restoration was completed in two phases. Circuit 1 was energised on September 20, followed by Circuit 2 on September 28, marking full recovery of the transmission corridor.

The Loiyangalani to Suswa line is a vital link for transmitting renewable energy from Marsabit County to the national grid.

LTWP contributes more than 10 per cent of Kenya’s electricity supply.

 Its collapse in recent years forced reliance on temporary bypasses that made the grid less stable and more expensive to maintain.

Officials said completion of permanent repairs restores full operational capacity and supports Kenya’s renewable energy plans under Vision 2030 and international climate commitments.

Share this story
New KMA directive on seafarer training gets industry backing
For decades, the maritime sector has operated under a narrow definition of safety that privileged physical hazards while remaining largely silent on social harm. 
Funding woes scuttle key Seafarers Council's work
Kenya ratified the MLC in 2013, but setting up a functional council has since proved a challenge.
Developers condemn reports that most city buildings are unsafe
They have also described the statement as alarming and could cause unnecessary panic to Kenyans.
Win for Kenya as AGOA agreement extended for 3 years
Ministry of Trade says discussions are ongoing on bilateral trade agreement that will cover other key sectors and further cement Kenya’s long-standing partnership with the United States.
Leases, looting and a grounded fleet expose turbulence at KQ
Aircraft sent for routine maintenance are taking longer to return to service, delayed by shortages of critical spare parts.
.
RECOMMENDED NEWS