From Bomas to major roads and airports: How contract blunders are hurting taxpayers
Business
By
Macharia Kamau
| Nov 17, 2026
Construction of the Bomas International Convention Centre on April 20, 2026. Turkish contractor Summa had initially been awarded the contract. [File, Standard]
Taxpayers are facing yet another hefty bill for the cancellation of the tender awarded to a Turkish firm to build the Bomas International Convention Centre (BICC), which was awarded to China Road and Bridge Corporation after the Kenya Defence Forces took over the project.
The government stripped the Turkish contractor Summa of the BICC project and handed the repriced contract to CRBC, which has already had a toll on taxpayers following a Sh13 billion escalation in the cost of the project. The cost of the project has gone up to Sh45.1 billion after it was handed over to CRBC from the Sh31.5 billion it was initially expected to cost.
Summa has not made a formal bid for payment for the contract termination, which analysts say should be a major concern for the Government.
READ MORE
ICPAK urges State to hire qualified accountants to curb financial mismanagement
Tea reforms boost farmers' earnings and access to credit
East African businesses turn to outsourced logistics as regional trade grows
Kassait wins global privacy award as Kenya and EU advance data adequacy deal
Kenya backs AU's new financing model pushing to raise Sh155b
Parliament think tank faults Ruto for unfulfilled promises and rising debts
Remittance slump threatens festive season spending
Treasury to seize dormant crypto wallets in proposed policy changes
African universities develop first open-source curriculum on forgotten foods
Crackdown on crypto begins as firms face Sh25m fine, imprisonment
The Bomas tender added to the latest in a growing list of cancelled tenders that are also costly to the taxpayer. Other major contracts cancelled by the current administration and proved costly include Adani deals for which it is expected to pay the Indian firm Sh5 billion and the Rironi-Mau Summit Road, for which it paid the consortium of French firms Sh7 billion to end the contract that was then handed over to CRBC and Shandong Hi-Speed.
The Jubilee Administration paid Sh9 billion for the cancellation of Jomo Kenyatta International Airport’s (JKIA) Greenfield Terminal. While Kenya did not pay penalties for the cancellation of the corruption-riddled Kimwarer and Arror dams, it has continued paying the Sh23 billion loans that had already been taken from the project financiers and disbursed to the contractor that later filed for bankruptcy.
Kenya also paid Sh1.4 billion for the cancellation of the Anglo Leasing security contracts. The risk of such penalties is growing with Kenya increasingly adopting the Public-Private Partnership (PPP) model of building infrastructure. In recent budget documents, Treasury said it faces potential liabilities to the tune of Sh413.8 billion for some 13 projects currently underway. This amount is expected to increase to Sh2.28 trillion over the 2029/30 financial year.
Analysts warn that the trend of terminating contracts has exposed Kenya to high project costs, as contractors could in future factor political or termination risk when bidding for projects, which could make infrastructure more expensive compared to other regions.
“This is a most unfortunate trend which exposes the country to higher bids in future as investors price in more project risks,” said Ken Gichinga, Chief Economist at Mentoria Economics.
“It can also create an avenue for unscrupulous officials to submit proposals with no intention of completing the project, knowing fully well they will still receive compensation.”
Economist Patrick Muinde said when new governments take over, they use flimsy reasons to cancel contracts, particularly those signed in the dying days or months of the previous regime, on manufactured grounds. The projects are then retendered and usually at a higher cost
“New administrations at both the national and county governments would cancel a contract on very flimsy grounds, only to re-tender the same project months later, sometimes at a higher contract price,” he said in an analysis on how government officials use tenders to siphon money from public coffers. In his analysis, Dr Muinde tracked major projects cancelled over the last 13 years and noted that Kenya could have lost Sh45 billion paid as penalties.
“When the same project re-appears for a fresh tendering, no answers are ever given as to how the earlier arguments advanced to justify the cancellation mysteriously vanished and the project reverted back as a strategic public investment. The National Treasury then quietly enters into a negotiation process to clear the associated contract penalties, often paid under Article 223.”
“By the time the public gets to learn of those huge penalties, the project would have long been cleansed and lined up for new contractors with connections and friendly to the administration in office. In certain instances, the same administration would cancel a project simply because the ‘right’ people are not the ones in the feeding trough or because the appointed political heads have changed either in a Cabinet or administrative reshuffle.”
He further noted the cancellations have been done by the very same people who were in the previous administration that approved the projects. In the case of President William Ruto, he was part of the Jubilee Administration that signed off on the major projects that he has cancelled.
These include the Rironi-Mau Summit road that continues to generate debate. The PPP Directorate, in a recent report, said the government would pay Sh7.32 billion to the Rift Valley Highway – a consortium of French firms – for the cancellation of the contract to build the Rironi-Mau Summit road.
The road, which is being developed through the PPP model, had been awarded to the consortium of Vinci Highways SAS, Vinci Concessions SAS, and Meridiam Infrastructure Africa Fund but was cancelled in 2024 on concerns of high toll fees and unfavourable terms for Kenya.
The project has since been handed to a consortium of China Road and Bridge Corporation (CRBC) and Kenya’s National Social Security Fund (NSSF), which will build the Rironi-Naivasha-Gilgil section, while Shandong Hi Speed will build the Gilgil-Nakuru-Mau Summit sections.
Ruto on Thursday defended the cancellation of the contract awarded to the French consortium, noting the Chinese firms have offered more value, which is seen in lower project costs as well as how much motorists would pay to use the road when it is commissioned.
“The road that we are building under the current programme is going to cost us Sh191 billion. Under the French contract, it was going to cost the government of Kenya Sh249 billion. There is a difference of close to Sh60 billion,” said Ruto, adding that the Chinese firms will build a 210-kilometre road compared to the 175KM that the French firms were to build.
Ruto also said the French had proposed a higher toll rate of Sh12 per kilometre that motorists would pay to use the road. This is in comparison to Chinese firms that will charge Sh8 per kilometre.
The PPP Directorate also disclosed that Kenya would pay Adani for contract termination but said the process is underway and the termination costs are yet to be determined.
Adani was in 2023 awarded a contract to build three electricity transmission lines and substantiations through the PPP model. Adani had presented Ketraco with a Privately Initiated Proposal (PIP) to expand power infrastructure. In the proposal, Adani Energy Solutions was to build three transmission lines totalling 371 km and three substations, including the 206-kilometre, 400kV Gilgil-Thika-Malaa-Konza line. The projects will cost $907 million (Sh117.91 billion).
It would then operate and maintain the infrastructure for 30 years while charging electricity consumers to recoup their investments.
The award was, however, cancelled in 2024 following a directive by President William Ruto citing the indictment of Adani executives in the US. Also cancelled was the planned takeover of the JKIA by Adani Airport Holdings. This, however, did not attract any penalties as the deal had not been signed.
Even before the challenges with the US authorities, Kenya had rejected the Adani deals for, among other factors, the failure to undertake proper public participation, lack of transparency and the risk of high cost of electricity and increased charges for travellers through JKIA.
The Directorate noted that the project was cancelled before it reached financial close following the “disqualification of the proponent due to new information on their credibility”.
The PPP directorate has also disclosed that the government is set to pay for the cancellation of two contracts under the roads annuity programme. It has already terminated the contract for Road Annuity Lot 32 of the Annuity Programme for the construction and rehabilitation of a 67 kilometre road to augment the existing road network from Illasit to Taveta through Njukini. The contractor was paid about Sh438 million, according to the report by the PPP Directorate.
It also terminated the contract for Road Annuity Lot 3 that entailed construction and rehabilitation of Wajir–Habaswein–Samatar (68 kilometres) and Rhamu-Mandera (75 kilometres), but did not disclose how much was paid to the contractor.
Other past projects that have been costly to Kenya include the Anglo Leasing contracts, which involved more than a dozen single-sourced, multi-billion shilling government security and infrastructure contracts awarded to shell companies. Among the things the companies were supposed to deliver were a tamper-proof passport printing system, forensic laboratories for the police and intelligence and counter terrorism facilities.
Kenya, however, suspended the contracts after discovering that they were fraudulent schemes designed to siphon public funds through nonexistent shell companies and heavily inflated prices.
Nevertheless, the government in May 2014 paid Sh1.4 billion to settle the legal disputes and terminate the remaining claims on the Anglo Leasing contracts.
In 2016, the government also paid Sh9.6 billion to Chinese firms Anhui Construction Engineering Group and China Aero-Technology International Engineering Corporation for the cancellation of the Sh65 billion JKIA Greenfield Terminal project. The government at the time cited funding constraints for contract cancellation. The state also said there was adequate capacity at JKIA following the rebuilding of existing terminals at the time.
The numerous and costly cancellations are seen as stemming from procuring entities ignoring statutory safeguards. These include sections of the Public Procurement and Asset Disposal Act (PPADA), 2015, which bar accounting officers from cancelling a tender once a notification of award has been issued.
In several determinations, the Public Procurement Administrative Review Board (PPARB) has repeatedly censured ministries and state corporations for arbitrarily terminating tenders without legal justification, bypassing mandatory bidder notifications and re-advertising the exact same projects at inflated prices.
When state agencies breach Section 63 of PPADA, aggrieved companies routinely win hefty damages at the Review Board, the High Court, or international arbitration tribunals.
“The Board has in the recent past noted an increased number of incidences where Procuring Entities are terminating procurement processes arbitrarily without following the law and thereafter proceeding to re-advertise, evaluate and award the same tenders afresh pursuant to the said re-advertisement while in some cases even ignoring the decisions made by the Board and the court,” said the PPARB in a past determination.
“The Board notes that where the decision of a procuring Entity to terminate a procurement process is challenged before the Board, the procuring Entity is under a duty to place sufficient reasons or evidence before the Board to justify and support the termination of the procurement process under challenge."
While the government has turned to Public Private Partnerships (PPPs) to fund mega-infrastructure without immediately inflating headline public debt, the Draft 2027 Budget Policy Statement shows that these off-balance-sheet deals carry significant risks that could turn into liabilities when any of these PPP deals are terminated.
The budget document shows that Kenyans could pay Sh413.8 billion in the unlikely event that all the projects are cancelled. This figure represents only the contracts already signed and Treasury projects; once more projects are approved, taxpayers' total termination exposure could surge nearly six-fold to Sh2.28 trillion by the 2029/30 financial year.
“PPP contingent liabilities arise mainly from termination payments that would fall due if a Project Agreement ended early. Maximum exposure under signed agreements is estimated at Sh413.8 billion (1.8 per cent of GDP) in FY 2027/28, declining to Sh387.6 billion (1.5 per cent of GDP) in FY 2029/30,” said Treasury in the BPS.
“Approved projects expected to reach commercial close over the medium term would add up to Sh1.67 trillion (6.6 per cent of GDP), and projects awaiting approval a further Sh217.7 billion (0.9 per cent of GDP), bringing total maximum exposure to Sh2.28 trillion (nine per cent of GDP) in FY 2029/30.”
ICPAK urges State to hire qualified accountants to curb financial mismanagement
ICPAK has called on the national and county governments to employ qualified accountants to ensure timely and proper auditing and sound financial planning in the public sector.Tea reforms boost farmers' earnings and access to credit
Tea reforms have seen tea growers benefit from an increase in green leaf payment from Sh16 to Sh30 per kilogramme.East African businesses turn to outsourced logistics as regional trade grows
The growth of online commerce is increasing demand for transportation services covering the entire supply chain.Kassait wins global privacy award as Kenya and EU advance data adequacy deal
The milestone brings Kenya closer to becoming the first African country to secure a mutual data adequacy arrangement with the EU.From Bomas to major roads and airports: How contract blunders are hurting taxpayers
The government stripped the Turkish contractor Summa of the Bomas project and handed the repriced contract to CRBC, which has seen the cost of the project rise to Sh45.1 billion.MOST READ