Weak oversight, costly delays sink billions in donor funds Auditor

Auditor General Nancy Gathungu before the National Assembly's Cohesion Committee at Continental House,Parliament,Nairobi . April 15th,2025. [Elvis Ogina,Standard]

Auditor General Nancy Gathungu has raised questions on Sh4.8 billion interest payment incurred by donor funded projects in the Financial Year 2023/24 which could have been avoided.

During the year under review, Gathungu said the audit revealed that avoidable interest payments amounting to Sh4.8 billion were incurred across 17 donor funded projects due to delayed settlement of certified works and contractor's invoices.

Premium Article

Get Full Access for Ksh299/Week.

Uncover the stories others won't tell. Subscribe now for exclusive access.
Continue Reading  →
What you get
  • Unlimited access to all premium content
  • Ad-free browsing experience
  • Mobile-optimised reading
  • Weekly newsletters & digests
Pay via
M - PESA
VISA
Airtel Money
Secure Payments Kenya's most trusted newsroom since 1902