State lacks title deeds for Sh186.8m water and sanitation project land
Real Estate
By
Frankline Sunday
| Dec 16, 2021
The government does not have title deeds to Sh186.8 million worth of land parcels acquired for a water and sanitation project, funded by the African Development Bank (AfDB).
According to the Auditor General’s report on the Kenya Towns Sustainable Water Supply and Sanitation Programme, State agencies acquired the land for the Sh11 billion project without obtaining the ownership documents, exposing taxpayers’ funds to misuse.
“Although the sale agreements with the vendors for the respective parcels of land were provided for audit verification, there was no evidence that title deeds had been acquired,” Auditor General Nancy Gathungu said. “In the circumstances, it has not been possible to ascertain the ownership status of the parcel of land amounting to Sh186.8 million.”
The Kenya Towns Sustainable Water Supply and Sanitation Programme was initiated in 2016 to develop water supply infrastructure in 19 towns and sanitation infrastructure in 17 towns.
READ MORE
Treasury goes for UAE loan as IMF cautions of debt situation
Traders claim closure of liquor stores, bars near schools punitive
Adani fallout is a lesson on accountability and transparency fight
Sustainable finance in focus for Kenyan banks as Co-op Bank feted
Inside battle for control of Bamburi Cement
What forcing Google to sell Chrome could mean
How talent development is shaping Kenya's tech future
Street-style snappers reclaim the heart of Nairobi
Huawei, charity partners to empower women with digital skills in Kenya
African ministers champion ICT adoption for sustainable growth
For this project, the AfDB had given Sh10.9 billion in loans to the implementing agencies - Tana Water Works Development Agency and the Northern Water Works Development Agency.
Some of the towns set to benefit from the project include Kerugoya, Chogoria, Mandera, Muranga, Marsabit and Isiolo.
The two agencies have so far paid Sh162 million to 73 landowners in Mandera, Sh41.8 million to 22 owners in Chuka and Sh30 million to 20 landowners in Chogoria.
Gathungu said the project is unlikely to meet its December 2021 deadline as various contracts are yet to be honoured. “By June 30, 2020, the projects were not completed leading to the revision of the completed dates to November and December 2021,” she said.
Tana Water Development Agency blamed the delay on the slow disbursement of funds from the National Treasury.