ICT ministry in a spot over Sh12b foreign loans
News
By
Frankline Sunday
| Mar 11, 2022
Auditor General Nancy Gathungu addresses Kisumu County Assembly members on March 2, 2021.[Denish Ochieng, Standard]
The Ministry of Information, Communication and Technology (ICT) is on the spot over Sh12 billion in loans taken from the governments of Italy and China to develop key infrastructure projects.
Auditor General Ms Nancy Gathungu (pictured) said the ministry had failed to provide proper documents for the loans that were later paid to Chinese technology firm Huawei and Italian infrastructure firm Impresa Costruzioni Maltauro (ICM).
“The payments made comprised of borrowings totalling Sh2.6 billion for data centre at Konza Technopolis, an amount of Sh608 million from China for National Optic Fibre Backbone project and a total of Sh9.2 billion for Konza Technocity,” Ms Gathungu said in the audit report for the financial year ended June 2021. “However, the payments were supported by photocopies of documents instead of original documents, which the management indicated were forwarded to the lender.”
“Consequently, it has not been possible to confirm the propriety of payments totalling to Sh12.5 billion,” she said.
READ MORE
Absa unveils Sh100bn asset finance plan
Kenya targets Sh230bn from indigenous knowledge assets
Young innovators secure backing to scale, attract investors
Packaged Githeri signals rise of ready-to-eat meals
Africa's $29.5 trillion mineral wealth: The unsent invoice the world owes
From insight to action: How small businesses grow
Del Monte's growing footprint in kenya's farm economy
Consumption outpacing recycling of waste, data shows
Why AI and biometrics will be key to stopping fraud in digital economy
In 2017, ICM was given the tender as general contractor to oversee construction of key infrastructure at Konza, with its scope of work including roads, water and sewerage facilities for phase one of the project.
The first phase, which also includes a recycling facility, bulk water treatment plant, fibre optic links and a power station, was expected to attract 30,000 residents, 7,500 knowledge workers and 16,700 other workers upon completion.
As of June last year, however, civil works at Konza stood at 56 per cent while construction of horizontal infrastructure stood at 60 per cent.
This is the second time in as many years that the Auditor General is flagging payments made to contractors associated with the Konza Technopolis project.